Re: Remaining tasks on requirements

From
Mark Little <>
Date
2001-04-26T09:14:30+00:00
ID
007901c0ce31$2885ca70$
Thread
Re: Remaining tasks on requirements
> After our f2f meeting it is time to finalize our
> requirement/model/terminology document.
>
> Peter, Alastair and Mark (Little): are you guys willing to update the BT
> model's group draft with the results of the f2f that my document meant to
> capture?
> Also the agreed requirements list needs to be cleaned up of editorials.

I think we can work for a deadline of (roughly) a week before the next
face-to-face in Mt Laurel. That should give people a time to read it and get
comments ready for the meeting. However, I think that this is still going to
be an iterative process, and depending upon what the other subcommittees
come up with I would not be surprised if we're changing the document in
June. Hopefully such changes will be minimal though.

All the best,

Mark.

-----------------------------------------------------------------------
SENDER : Dr. Mark Little, Architect (Transactions), HP Arjuna Labs
PHONE  : +44 191 206 4538, FAX : +44 207 670 1964