PRD03- Pt 2, 4.11.12 "must" -> "shall" x 3

From
Alex Brown <>
Date
2011-02-27T11:48:16+00:00
ID
Thread
PRD03- Pt 2, 4.11.12 "must" -> "shall" x 3
Current text reads:

[...] it must be one of these two processing orders. If processing row-at-a-time, the sequence must be produced by processing each row in turn, from smallest to largest column value (e.g., A1, B1, C1). If processing column-at-a-time, the sequence must be produced by processing each column [...]