Dear TC members,

in the past weeks we have discussed a schedule for ODF-Next, and it
seems to me we reached consensus on a two year schedule for ODF 1.3,
based on 4 Committee Drafts. 

Having a schedule (regardless what it looks like in detail) is a
critical item for our daily work. That's because the schedule tells all
of us by when we must have our proposals ready, and when we can expect
them in a specification. The schedule therefore is the basis for
planing our own personal work on ODF 1.3.

It is therefore important that we are all
familiar with the schedule, and that we stay with it whenever possible.
I therefore propose that we formally agree on the schedule in a
resolution. Please note that this does not mean that the schedule
cannot be changed if there are good reasons for this. It can be
changed, but this would require also a formal resolution.

Below is what I would like to propose as resolution text. I
intentionally have not used any CSD numbers, because it is not unlikely
that we need additional CSDs. For instance if  we have approved a CSD
and want to send it out for public review, but then notice an issue we
think needs to be addressed first.

Resolution:

-The ODF TC aims to develop ODF 1.3 as a sequence of committee
specification drafts (CSDs).
Committee specification drafts shall be ready for approval by the TC
every 6
months. 

- The first committee specification draft shall be ready for approval
in
September 2011, subsequent CSDs in March 2012, September 2012 and March
2013. Additional CSDs are permitted.

- For the September 2011 CSD, no proposal shall be integrated after
July 2011. 

- For the March  2012 CSD, no proposal shall be integrated after
January 2012. 

- For the September 2012 CSD, no proposal shall be integrated after
July 2012. 

- After the September 2012 CSD, no new features shall be integrated
into the
ODF specification. Exceptions from this rule shall be granted
only if the TC is confident that the new feature does not break, and
that it further gets implemented.

- The March 2013 CSD  shall be advanced to an OASIS standard. It may be
approved
earlier than March 2013 if no proposals or severe issues are
outstanding.

Best regards

Michael

-- 

Michael Brauer | Oracle Office Development

Phone: +49 40 23646 500 

Oracle Office Global Business Unit

ORACLE Deutschland B.V. & Co. KG | Nagelsweg 55 | 20097 Hamburg

ORACLE Deutschland B.V. & Co. KG

Hauptverwaltung: Riesstr. 25, D-80992 München

Registergericht: Amtsgericht München, HRA 95603

Komplementärin: ORACLE Deutschland Verwaltung B.V.

Rijnzathe 6, 3454PV De Meern, Niederlande

Handelsregister der Handelskammer Midden-Niederlande, Nr. 30143697

Geschäftsführer: Jürgen Kunz, Marcel van de Molen, Alexander van der Ven

Oracle is committed to developing practices and products that
help protect the environment
← Prev in month ← Prev in thread