Process and timeline for V1.1

From
Philpott, Robert <>
Date
2003-04-18T16:42:49+00:00
ID
Thread
Process and timeline for V1.1
After researching the 1.0 process and the current OASIS
requirements and bouncing it off Prateek, Eve, and Jeff, I've put
together the attached timeline for everyone to review and comment.

 

In order to use this as the schedule, it means that on the 22-April
call, we MUST make final decisions on what we will include in V1.1. We then
have to have the spec's ready for SSTC Last Call on 29-April.

 

Note that we probably have a bit of slack in item #8 below,
so we might squeeze out an extra week for our internal reviews, etc.  But
I think we should shoot for the dates below.

 

Note that we need to get at least 3 attestations of
implementation for the V1.1 spec.  So PLEASE start thinking about whether
your company can provide that.  I am currently assuming we need to follow
the process we used for V1.1, where I think we obtained attestations for each major
area of functionality (e.g. Browser/POST, Browser/Artifact).  Do folks
feel it's necessary to follow this same model for the 1.1 release?

 

 

 

Here's the SSTC's "Committee Last Call
Process": 

           
http://lists.oasis-open.org/archives/security-services/200202/msg00176.html

and the OASIS standardization process:

           
http://www.oasis-open.org/committees/guidelines.php#spec_standard

 

To me, it seems the earliest we could get the specs to OASIS
is 15-July for an OASIS vote in August.

 

It's now 18-April. Given the discussions on Tuesday's
call, I honestly don't believe we can vote to start the SSTC Last Call
period until probably the end of this month (29-April).  I personally
think this is very aggressive, but possibly doable. However, with our
SSTC-mandated 2-week Last Call period, I don't see how we can realistically
make a request to OASIS to start their 30-day Public Review period until toward
the end of May. This means we can't close the public review, work on any
public comments, and prepare the submission documents until the end of
June.  We have to have stuff in by the 15th of a month. 
Since it doesn't look, to me at least, that it's possible to do
this in June, it pushes us to July 15 for OASIS submission.

 

I think the timeline looks something like this:

 

 
[Now] The SSTC produces working drafts of the
     specs.  

 
[Target: 29-April] When the TC agrees that the draft
     specs are ready for TC last call, the Chairs announce the start of the TC
     "Last Call period" with at least a 2 week cutoff date. 
     The announcement is sent to the TC and the next version of OASIS News.

 
[Target: 13-May] Cutoff date for all Last Call input.

 
[Target: 20-May] All outstanding issues have been dealt
     with according to the last call process. The specs now become
     "Candidate Committee Spec's" and the TC addresses any
     outstanding non-normative editorial issues.

 
[Target: 27-May] Once editorial issues are resolved,
     the TC votes to turn the "candidate" spec into the official
     "Committee Spec".  

 
[Target: 28-May] The TC chairs must announce to OASIS
     that the Committee Spec is available for a 30-day Public Review period.

 
[Target: 1-July (1st Tuesday following
     30-day period)] The TC must do a final (re-)approval of the spec as a
     Committee Spec and vote to submit the Committee Spec to OASIS

 
[Target: 1-July] Chairs begin to prepare OASIS spec
     submission document which includes

 
  
Reference links to specs

  
Certification by at least 3 vendors successfully using
      the spec

  
Disposition of public review comments

  
IPR policy compliance statements

 
 
[Target: 15-July] The submission document must be
     submitted to OASIS by the 15th of the month

 
[Target: 1-August] OASIS will make the announcement of
     the TC's request for standardization of the committee spec by the 1st
     of the month.

 
[Target: 15-August] Voting will commence by the 15th
     of the month.

 
[Target: 31-August] Voting will complete at the end of
     the month.

 

Rob Philpott 