Tentative Schedule for Completing the Working Draft
Hello all, Robbie and I had a excellent discussion last week and would like to propose the following schedule for completing the UIML 4.0 working specification: July 20: Jim finishes cleaning up the specification and cleans up remaining issues. July 21 to August 3: Committee review to finalize and remaining issues. We would especially like for Jean and Heinz-Josef to review the specification in its entirety (if possible). I think their fresh perspectives would be extremely helpful in finalizing the revision. August 4 to August 17: Final revisions based on internal review. At this point we should have completed and polished version of the specification. Feedback is welcome! James Helms Director of Research and Development Harmonia, Inc. P.O. Box 11282 Blacksburg, VA 24062 Office: (540) 951-5900 x 205 Cell: (540) 558-9722