17 weeks before we need to start OASIS processes -- How can we best use them?


Week # Dates Scheduled activities Completed? 1 2-8 February 2 9-15 February 3 16-22 February 4 23 February - March 1 5 2-8 March 6 9-15 March 7 16-22 March 8 23-29 March 9 30 March - 5 April 10 6-12 April 11 13-19 April 12 20-26 April 13 27 April - 4 May 14 5-11 May 15 12-18 May 16 19-25 May 17 26 May - 1 June -- Best, Kris Kristen James Eberlein Chair, OASIS DITA Technical Committee Principal consultant, Eberlein Consulting www.eberleinconsulting.com +1 919 682-2290; kriseberlein (skype)