MINUTES OF ATLANTIC UBL TC MEETING WEDNESDAY 16 MAY 2012
ATTENDANCE
Kenneth Bengtsson
Peter Borresen
Jon Bosak (chair)
Andy Schoka
STANDING ITEMS
Additions to the calendar:
http://ubl.xml.org/events
None.
Review of Pacific call minutes
No comments.
UBL 2.1 PRD3 PSC DELIVERABLES
Review of the changes suggested last week:
http://lists.oasis-open.org/archives/ubl-psc/201205/msg00005.html
http://lists.oasis-open.org/archives/ubl/201205/msg00012.html
http://lists.oasis-open.org/archives/ubl/201205/msg00014.html
AGREED to adopt these changes pending a wider review of the schemas.
PLB: Item 6 should be adding LineReference (not OrderLineReference)
to LineItem, cardinality 0..n. Cardinality for item 5
(ItemPriceExtension on LineItem) is 0..1. Arianna was instructed to
make TaxTotal on LineItem (item 4) 0..1, but perhaps this should be
0..n. Arianna has already been given the changes.
ACTION: PLB to check with interested PSC members regarding
cardinality of TaxTotal.
JB: Since it appears that the model in eDoCreator will have been
updated by the end of this week at the latest, we will accommodate a
personal request of the chair by cancelling next week's TC calls
while SGTG makes another test build.
DEFINITION REVISION
See Pacific call minutes for status.
JB: All content origination groups for UBL 2.1 (procurement, sales
reporting, CPFR, utilities, tendering, transport) should prepare for
an intensive review of edits to the data dictionary definitions
beginning (probably) week after next.
ACTION: AS to send JB 11179 definition guidelines for
consideration.
SGTG SCHEDULING
As noted above, we expect changes to be complete by the end of this
week at the latest, which will allow generation of another test build
next week.
TC CONCALL SCHEDULE
Note that calls for next week have been cancelled.
Week of 2012.05.14 Regular schedule
Week of 2012.05.21 *** CANCELLED ***
Week of 2012.05.28 Regular schedule
Week of 2012.06.04 *** CANCELLED ***
Week of 2012.06.11 Regular schedule
Week of 2012.06.18 Regular schedule
Week of 2012.06.25 Regular schedule
Jon Bosak
Chair, OASIS UBL TC
==================================================================
TRACKING ITEMS
BUSINESS DOCUMENT ENVELOPE TASK GROUP
On hold pending progress of the parallel work in UN/CEFACT.
NDR WORK
ACTION (2012.01.04): GKH to combine his previous analysis with
BH's work to make a straw man for review.
Pending.
NDR CHECK (NIST TOOL)
On hold while working on NDR revision.
UBL 2.1 NDR ILLUSTRATIONS
UBL 2.0 NDR IMPLEMENTATION GUIDE WIKI
http://wiki.oasis-open.org/ubl/NDR_2.0_Implementation_Guide
CCTS 2.01 DMR
ACTION (2009.06.30): TM to circulate a draft CCTS 2.01 DMR
to the TC for review.
Pending.